Ata construction, industrial and trading company




Download 332.12 Kb.
Pdf ko'rish
bet14/29
Sana03.05.2023
Hajmi332.12 Kb.
#56193
1   ...   10   11   12   13   14   15   16   17   ...   29
Bog'liq
ita0043 (1)
Joriy 1, nutq, doston temirov 27kazus, pochta xarajat ipk, kroossword1
 
Article 51: 
If the competent court approves the arbitral award, it must decide its execution 
and such decision is final. If, otherwise, the court decides the nullity of the 
award, its decision is subject to challenge before the Court of Cassation within 
thirty days following the date of notifying that decision. The final decision 
nullifying the award results in extinguishing the arbitration agreement. 
IV. 
THE RESPONDENT’S JURSIDICTIONAL OBJECTIONS 
A. 
The Respondent’s Position 
63. 
It is the Respondent’s position that the Centre lacks jurisdiction ratione temporis 
over the Claimant’s claims, and that the Tribunal thus lacks competence to rule upon 
these claims, for the following reasons: 


- 26 - 
First
As Claimant has acknowledged, “[t]he Turkey-Jordan BIT entered into force on 
23 January 2006.” Cl. Mem., ¶ 99; see also ICSID Database of Bilateral 
Investment Treaties – Treaties of Jordan, available at icsid.worldbank.org 
(Exhibit R-5). The record establishes, however, that in September 2000, ATA 
and APC each gave notice of an intent to commence arbitration, and on 29 
October 2003, APC filed its annulment action challenging the arbitral tribunal’s 
Final Award of 30 September 2003. See Cl. Mem., ¶¶ 33, 66; see also ATA 
Notice Letter (6 Sept. 2000) (Exhibit R-6); APC Notice Letter (10 Sept. 2000) 
(Exhibit R-7). 
, it is well established that, unless a contrary intent appears on the face of the 
treaty, a bilateral investment treaty (or “BIT”) will not apply to a dispute that has 
arisen, fully developed, and been extensively pursued before the BIT’s entry into 
force. Here, the dispute in question had not only had [sic] arisen, but had been 
extensively litigated, in both arbitral and judicial proceedings, for a period of 
nearly six years before the BIT’s entry into force. 
By 23 January 2006, all proceedings in both the arbitration and the annulment 
action before the Court of Appeal had been concluded, with nothing remaining 
but the issuance of that Court’s judgment of annulment (which occurred on 24 
January 2006, the day following the BIT’s entry into force) and the subsequent 
appellate proceedings in the Court of Cassation. 
By any reasonable assessment, the pertinent dispute had arisen, and the parties in 
interest (APC and ATA) had fully developed and articulated their respective 
positions and arguments, long before the Turkey-Jordan BIT’s entry into force on 
23 January 2006. All of the material facts and arguments that ATA now seeks to 
present, except the court judgements themselves, were presented and addressed 
before the Court of Appeal – albeit without being phrased in the terminology of 
public international law. ATA’s complaint before this Tribunal is not that the 
Jordanian courts committed substantively new violations of its (newly created) 
rights after the BIT entered into force; rather, it is that the Final Award should 
not have been annulled under the Jordanian Arbitration Law and that Respondent 
owes ATA the damages that were awarded in the Final Award, plus related relief.
In substance, this is the same dispute that was presented to, and fully litigated 
before, Jordan’s Court of Appeal. 
By no reasonable reading of Claimant’s own submissions and description of this 
dispute can it be said, as ATA now asserts, that “the Claimant’s dispute with the 
Respondent arose on 16 January 2007 when the Jordanian Court of Cassation 
delivered the final judgment in the domestic proceedings between the Claimant 
and APC, thereby annulling the Final Award and extinguishing the arbitration 
agreement contained in the Contract.” Cl. Mem., ¶ 159. The proceedings in the 
Court of Cassation represented a continuation of the case presented to the Court 
of Appeal well before 2006, and in substance, a continuation of the original 
dispute, which began in 2000. The Court of Cassation’s judgement affirmed the 
judgment of the Court of Appeal, on the basis of the same record and in the face 
of the same substantive arguments. No new or different dispute arose on 16 
January 2007 – or at any time after 23 January 2006. 


- 27 - 
Second
It stretches language and legal reasoning beyond the breaking point to state, on 
these facts, that Claimant’s interest in the arbitral damages award, which was 
subject to judicial review for annulment in the ordinary course, constituted an 
“investment” that “existed” at the time of the Turkey-Jordan BIT’s entry into 
force on 23 January 2006. On that date, nothing remained of the alleged, 
underlying “investment;” all that remained was the continuation of ongoing 
Jordanian court proceedings, which concerned not the underlying contract or 
performance but the legality of the subsequent arbitral award. 
, this Tribunal lacks jurisdiction because, by its terms, the Turkey-Jordan 
BIT “shall apply to investments existing at the time of entry into force as well as 
to investments made or acquired thereafter.” Jordan-Turkey BIT, art. IX(1) 
(Exhibit C-1). ATA’s claims are not predicated on any alleged “investment” 
existing at the time of the Turkey-Jordan BIT’s entry into force, or made or 
acquired thereafter. On the contrary, ATA’s claims are predicated on its Contract 
with APC of 2 May 1998, which was executed nearly eight years before the 
BIT’s entry into force and in connection with which ATA had (a) fully 
completed its performance and “handed over control” by 9 December 1999, and 
(b) subsequently obtained a liquidated damages award (as later annulled by the 
Jordanian courts) on 30 September 2003. 
If there is jurisdiction ratione temporis over ATA’s claims here, then it is 
difficult to perceive when this jurisdictional limitation ever properly applies. A 
legal claim presumably never would be barred for temporal reasons, so long as 
the claimant continues to assert it and phase it in the language of a BIT, or can 
relate it to an allegedly underlying “investment” even if that investment was 
made and terminated many years before the applicable BIT’s entry into force. 
[emphasis in original] 
64. 
More particularly, regarding the Respondent’s first jurisdictional objection to the 
effect that the BIT does not apply to disputes that predate its entry into force, the 
Respondent argues as follows: 
Many BITs contain clear language that prohibits their application to disputes that 
predate their entry into force. The Turkey-Jordan BIT contains no express 
language to this effect. However, ICSID tribunals have consistently held that, in 
“the absence of specific provision for reciprocity,” it is proper to infer that 
“disputes that may have arisen before the entry into force of the BIT are not 
covered.” This approach gives effect to the strong and longstanding presumption 
against retroactivity that is expressed in the Vienna Convention on the Law of 
Treaties and embedded in customary international law. Under this settled 
principle, the Turkey-Jordan BIT does not apply to any dispute that arose before 
it entered into force, on 23 January 2006. 
[…] 


- 28 - 
Here, ATA does not claim to be seeking retroactive application of the Turkey-
Jordan BIT: that is, it does not expressly argue that the Turkey-Jordan BIT should 
be applied to a “dispute” that predated the BIT’s entry into force. Rather, ATA 
contends that “the Claimant’s dispute with the Respondent arose on 16 January 
2007 when the Jordanian Court of Cassation delivered the final judgment in the 
domestic proceedings between the Claimant and APC, thereby annulling the 
Final Award and extinguishing the arbitration agreement contained in the 
Contract.” Cl. Mem., ¶ 159. 
It is apparent, however, that a “dispute,” as that term is defined in the ICSID 
jurisprudence, both existed and had been extensively pursued long before the 
issuance of the Court of Cassation’s judgement on 16 January 2007. Claimant’s 
own recital of the facts shows that in September 2000 (i.e., more than five years 
before the BIT’s entry into force) ATA and APC each gave notice of an intent to 
commence arbitration, and on 29 October 2003, APC filed its annulment action 
challenging the arbitral tribunal’s Final Award of 30 September 2003. See Cl. 
Mem., ¶¶ 33, 66; see also ATA Notice Letter (6 Sept. 2000) (Exhibit R-6); APC 
Notice Letter (10 Sept. 2000) (Exhibit R-7). 
In these circumstances, it is an understatement to say that the dispute had 
“crystallized.” It had been extensively litigated long before the BIT’s entry into 
force on 23 January 2006. By that point, all proceedings in both the arbitration 
and the annulment action before the Court of Appeal had been concluded, with 
nothing remaining but the issuance of that Court’s judgment of annulment (which 
occurred on 24 January 2006, the day following the BIT’s entry into force) and 
the subsequent appellate proceedings in the Court of Cassation. 
The question, then, is whether a new and subsequently different “dispute” arose 
on 16 January 2007, or at any other time after 23 January 2006. 
[…] 
The same analysis and result apply here, but with greater force. No new or 
different dispute arose in this case on 16 January 2007 – or at any time after 23 
January 2006. The proceedings before the Court of Cassation represented the 

Download 332.12 Kb.
1   ...   10   11   12   13   14   15   16   17   ...   29




Download 332.12 Kb.
Pdf ko'rish

Bosh sahifa
Aloqalar

    Bosh sahifa



Ata construction, industrial and trading company

Download 332.12 Kb.
Pdf ko'rish