III.TEXNIK – IQTISODIY QIYOSLASH NATIJASIDA ELEKTR STANSIYALARI VA PODSTANSIYALARINI BOSH SXEMASINI TANLASH (2 – variant uchun)




Download 245,85 Kb.
bet3/5
Sana16.05.2024
Hajmi245,85 Kb.
#238876
1   2   3   4   5
Bog'liq
30-21 EE

III.TEXNIK – IQTISODIY QIYOSLASH NATIJASIDA ELEKTR STANSIYALARI VA PODSTANSIYALARINI BOSH SXEMASINI TANLASH (2 – variant uchun).

Texnik – iqtisodiy hisobni minimal keltirilgan sarf – xarajatlar boʻyicha hisoblanadi.


Z = Рn·КТ+ I (mln.so’m) (34)


bunda, RN–normativ koeffitsent boʻlib 0,15ga teng;


KT– podstatsiyalarga oʻrnatilgan transformatorlarni tannarhi boʻlib quyidagicha aniqlanadi.

КТ= К0 ·nT (mln so’m) (35)


I = Uа.т + UЭ (mln so’m) (36)


nT – transformatorlar soni;
K0 – bitta transformatorning tannarhi;
I–yillik ekspluatatsiya xarajatlari quyidagicha aniqlanadi(mln.soʻm)
Ua.t – amortizatsiya uchun ajratilgan sarf–xarajatlar quyidagichahisoblanadi.

Uа.т =[(Ра о)/100] Кт (mln so’m) (37)


bunda,
Ra – amortizatsiya uchun ajratilgan normasi 6,3 % ga teng;
R0 – podstansiyani hizmati va taʼmirlash uchun ajratilgan xarajatlar 3 % ga teng;
UE – bir yillik elektr energiya isrofini narhi, mln. soʻm
UЭ =  · Э (mln so’m) (38)
bunda, –I kVat. soat elektr energiya isrofi uchun toʻlanadigan tannarhi 420 soʻm /kVt.
soat
I– variant

Z = R N· K T1+ I1=0,15*3245.037+617.85 = 1104.61 (million so'm)


Z = R N· K T2+ I2=0,15*6490+916 = 2192.16 (million so'm)


­K T1 = K 0 · n T =1*3245.032=3245.032 (million so'm)


­K T 2= K 0 · n T =2*3245.032=6490.047 (million so'm)


I1 = U a.t1 + U E1 = 301.78 + 316 = 617 (million so'm)


I2 = U a.t2 + U E2 = 301.78 + 615 = 1218.65 (million so'm)


U a.t1 = 0.093*Kt1=0.093*3245.037=301.78 (million so'm)


U a.t 2= 0.093*Kt2=0.093*6490.074=615.07 (million so'm)


U E1 = =738638.1 *495/100000=316 (million so'm)


U E2 = =1242577*495/100000=615 (million so'm)


II – variant

Z = R N· K T1+ I1=0,15*6084+667 = 1844 (million so'm)


Z = R N· K T2+ I2=0,15*12162+1019 = 3674 (million so'm)


­K T1 = K 0 · n T =1*6084=6084 (million so'm)


­K T 2= K 0 · n T =2*6084=12168 (million so'm)


I1 = U a.t1 + U E1 = 565 + 365 = 931 (million so'm)


I2 = U a.t2 + U E2 = 1131 + 717 = 1849 (million so'm)


U a.t1 = 0.093*Kt1=0.093*6084=565 (million so'm)


U a.t 2= 0.093*Kt2=0.093*12168=1131 (million so'm)


U E1 = =638517*495/100000=365 (million so'm)


U E2 = =1449953 *495/100000=717 (million so'm)





Download 245,85 Kb.
1   2   3   4   5




Download 245,85 Kb.

Bosh sahifa
Aloqalar

    Bosh sahifa



III.TEXNIK – IQTISODIY QIYOSLASH NATIJASIDA ELEKTR STANSIYALARI VA PODSTANSIYALARINI BOSH SXEMASINI TANLASH (2 – variant uchun)

Download 245,85 Kb.