Bog'liq English 20 ball What is a Gantt chart?
A Gantt chart is a type of bar chart that represents a project and plots tasksacross a timeline. It’s one of the most commonly used project management tools.
The typical Gantt chart format lists tasks vertically down on the left, whilea timeline runs horizontally across the top of the chart. Horizontal bars, or Gantt bars, represent each task's progress, duration, and start and end dates. A Gantt chart also shows milestones, assignees, and dependencies between tasks (See chart 1).
Chart 1. Gantt chart.
|
201
8
|
2019
|
2020
|
Oct- Dec
|
Jan
-
Ma r
|
April
-June
|
July
-Sep
|
Oct
-
Dec
|
Jan
-
Ma r
|
April
-June
|
July
-Sep
|
Oct
-
Dec
|
Protocol Developme
nt
|
|
|
|
|
|
|
|
|
|
Initial pitch to Cancer Research
UK
|
|
|
|
|
|
|
|
|
|
Final protocol
submission
|
|
|
|
|
|
|
|
|
|
Grant
awarded
|
|
|
|
|
|
|
|
|
|
Develop
recruitment materials
|
|
|
|
|
|
|
|
|
|
Obtain ethics
approval
|
|
|
|
|
|
|
|
|
|
Prepare
protocol manuscript
|
|
|
|
|
|
|
|
|
|
Phase I: Acceptabilit
y
|
|
|
|
|
|
|
|
|
|
Patient focus
groups
|
|
|
|
|
|
|
|
|
|
Stakeholder
focus groups
|
|
|
|
|
|
|
|
|
|
Data
analysis
|
|
|
|
|
|
|
|
|
|
Prepare qualitative data
manuscript
|
|
|
|
|
|
|
|
|
|
Phase II:
Feasibility
|
|
|
|
|
|
|
|
|
|
Data mining
|
|
|
|
|
|
|
|
|
|
Data
analysis
|
|
|
|
|
|
|
|
|
|
Phase III:
Research
|
|
|
|
|
|
|
|
|
|
Referral
messages sent
|
|
|
|
|
|
|
|
|
|
Follow-up
survey
|
|
|
|
|
|
|
|
|
|
Data
analysis
|
|
|
|
|
|
|
|
|
|
Prepare final outcomes
manuscript
|
|
|
|
|
|
|
|
|
|
Task 2. Prepare Gantt chart for the given activity. You work for a computer games company. Your manager has asked you to prepare a roughplan for a new project: a website to advertise a new computer game. Developa Gantt chart for this Project (Chart 2).
Chart 2. Gantt chart. This example Gantt chart is a simplified version. Gantt charts can contain more elements.
Task s
|
Weeks
|
1
|
2
|
3
|
4
|
5
|
6
|
7
|
8
|
9
|
1
0
|
1
1
|
1
2
|
1
3
|
1
4
|
1
5
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
DESCRIBING THE CHART
Task 1. Study the given materials.
To effectively describe a pie chart you should follow this answer structure:
Introduction
General overview
Specific features
Let's look in detail how to answer pie chart question.
IELTS pie chart Question:
The two pie charts below show the percentages of industry sectors' contributionto the economy of Turkey in 2000 and 2016.
Summarize the information by selecting and reporting the main features andmake comparisons where relevant.
And now let's learn how to describe IELTS pie charts by doing this example (See Chart 3).
IELTS pie chart answering strategy:
Introduction
The first paragraph you write is an introduction. The introduction is 1 or 2sentences, where you introduce your chart. In the introduction you have to paraphrase the information from your question and mention 2 important things:
In our example, I wrote the introduction this way:
The two pie charts illustrate how different industry sectors contributed to the economy of Turkey percentagewise in the years 2000 and 2016.
So, I just took the information from the question card and
paraphrased it insuch way:
show → illustrate
the percentages of industry sectors' contribution to the economy ofTurkey → how different industry
sectors contributed to the economy of Turkey percentage wise
in 2000 and 2016 → in the years 2000 and 2016.
pie charts = pie charts (don't change this!)
|
| |