Jadval Yakunlash davri uchun mehnat va mexanizm sarfi
|
bet | 18/31 | Sana | 03.02.2021 | Hajmi | 0,92 Mb. | | #13109 |
1.10 Jadval Yakunlash davri uchun mehnat va mexanizm sarfi
Me’yori xujat
|
Ishlar nomi
|
Ulchov birligi
|
Hajm
|
Mehnat sarfi, kishi soat
|
Mexanizm sarfi, mashsoat
|
Birlik,
|
Umumiy hajmga
|
Birlik
|
Umumiy hajmga
|
SHNK
4.02.28-96
T.28-31
|
YO‘lni tekislash
|
Km
|
38.3
|
1288,3
|
49341.89
|
102,21
|
3915.67
|
SHNK
4.02.28-96
T.28-28
|
Stantsiya yo‘llari
|
Km
|
9.58
|
842
|
8066.36
|
100,52
|
962.98
|
SHNK
4.02.28-96
T.28-29
|
Strelkali O‘tkazgich
|
Komp
|
24
|
110,26
|
2646.24
|
26,92
|
646.08
|
SHNK
4.02.28-96
T.28-33
|
YO‘l ko‘rsagich O‘rnatish
Ishchilar
Mashinistlar
|
Km
|
38.3
|
102
|
3906.6
|
11,06
|
423.598
|
Drezina
Platforma
|
Km
|
38.3
|
3,48
106
|
138.28
4059.8
|
20,45
|
783.235
|
SHNK
4.02.28-96
T.28-37
|
1km uchun material zapasi
Ishchilar
Mashinistlar
|
100 km
|
0.383
|
118,78
-
|
4549
|
-
22,27
|
8.53
|
SHNK
t.4.02.28-96
.28-35
|
Strelkali O‘tkazgich
|
100 komp
|
0,24
|
536,83
|
128.84
|
85,24
|
20.458
|
SHNK
t.4.02.28-96 t.28-39
|
Pere’ezdlarni joylashtirish
|
Pere’ezd
|
2
|
1288,3
|
2576.6
|
102,21
|
204.42
|
JAMI:∑ = 70910.1kishi soat ∑ = 6964.97 mash soat
Qurilishni tashkil etish kalendar grafiklari
Qurilishni tashkil etishning kalendar grafigida, quriladigan yangi temir yo‘l izining sxematik plani, asosiy ishlar hajmi, ularning bajarish ketma-ketligi va davomiyligi ko‘rsatilgan. Yangi temir yo‘l qurilishining kalendar rejasi 1 ilovada keltirilgan.
Unda quyidagi ishlar muddati keltirilgan:
Tashkiliy tayyorgarlik davri - 132kun
Yer ishlar: Ekskovator cho‘mich hajmi q = 1.6 m3 - 171kun
Ekskovator cho‘mich hajmi q = 1.6 m3 - 153 kun
Buldozer - 142 kun
Sun’iy inshotlarni barpo etish - 28kun
Yo‘l izini yotqizish - 60kun
Yo‘l izini 1- qatlamini ballastlash - 60kun
Yo‘l izini 2- qatlamini - 76kun
Bino va inshotlarni qurish - 396 kun
Yo‘lni topshirishdan avval bajariladigan ishlar - 72 kun
Qurilish uchun resurslar
1.6.1 Qurilish mashinalari, mexanizmlari va jihozlari
Qurilish uchun talab qilinadigan asosiy mashinalar va mexanizmlar loyiha ishlar hajmigaasoslangan holda, qurilish karxonalar mavjud bo‘lgan avtomobil parklarini etiborga olgan xolda jamlanadi. Qurilish uchun talab qilinadigan asosiy mashinalar va mexanizmlar talabi 1.11.-jadvalda keltirilgan.
1.11 Jadval Qurilish uchun talab qilinadigan asosiy mashinalar
va mexanizmlar grafigi
Nomlari
|
Ul-chov bir-ligi
|
Mashina mexanizm sarfi
|
Kundalik mashinalar soni
|
Birinchi 2017yil
|
Ikkinchi 2018yil
|
Tayyorgarlik davri
|
Asosiy ishlar davri
|
I
Kvartal
|
II
Kvartal
|
III
Kvartal
|
IV
Kvartal
|
I
Kvartal
|
II
Kvartal
|
III
Kvartal
|
1
|
2
|
3
|
4
|
5
|
6
|
7
|
8
|
9
|
10
|
Avtosamosvallar
|
Mash-smena
|
924
|
11
|
11
|
194
|
194
|
194
|
194
|
126
|
Buldozarlar
|
Mash-smena
|
16
|
16
|
16
|
-
|
-
|
-
|
-
|
-
|
Yo‘lni yotqizish krani
|
Mash-smena
|
19
|
-
|
-
|
-
|
6
|
7
|
6
|
-
|
Avto, gusenitsiali va bashen kranlari
|
Mash-smena
|
308
|
-
|
-
|
68
|
66
|
60
|
60
|
54
|
Platformalar
|
Mash-smena
|
11.4
|
-
|
-
|
-
|
-
|
11.4
|
-
|
-
|
Skreperlar
|
Mash-smena
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
Traktorlar
|
Mash-smena
|
43
|
6
|
7
|
5
|
5
|
5
|
5
|
5
|
Ekskavatorlar
|
Mash-smena
|
958
|
-
|
-
|
192
|
192
|
190
|
192
|
192
|
1.6.2 Qurilish resurslari, qurilish konstruktsiyalar,
jihozlar, xamashyolar
Talab qilinadigan qurilish resurslari, qurilish konstruktsiyalar, jihozlar, xomashyolar va energoresurslar loyiha ishlar hajmiga va KMK4.02.01-96 me’yorlariga asoslangan holda aniqlanib, qurilishning yillarga nisbatan taqsimlanadi. Qurilish resurslari, qurilish konstruktsiyalar, jihozlar, xomashyolartalabi1.12.-jadvaldakeltirilgan.
1.12 Jadval Qurilish resurslari, qurilish konstruktsiyalar, jihozlar, xamashyolar va energoresurslar grafigi
Xamashyolar nomi
|
Ulchov bir-ligi
|
Qurilish maydoni tayyorlash
|
Er ishlari
|
Sun’iy
Inshotlar
|
YO‘l izini yotqizish
|
Binolar
|
Umumiy
|
Ishlar hajmini davrlar bo‘yicha taqsimlash
|
2017 yil
|
2018 yil
|
I kvartal
|
II kvartal
|
III kvartal
|
IV kvartal
|
I kvartal
|
II kvartal
|
III kvartal
|
Tayyorgarlik davri
|
Asosiy ishlar davri
|
Oddiy g’isht
|
Ming dona
|
22.98
|
-
|
-
|
-
|
344.79
|
367.77
|
13.56
|
9.34
|
68.96
|
68.96
|
68.96
|
68.96
|
68.96
|
Sement
|
Tn
|
17.24
|
-
|
1609.02
|
30.65
|
444.4
|
2101.31
|
9
|
8.24
|
416.81
|
416.81
|
416.81
|
416.81
|
416.81
|
Qum
|
M3
|
76.6
|
957.75
|
2910.8
|
57.47
|
1059.3
|
5061.92
|
38.3
|
38.3
|
457.4
|
762.07
|
610.2
|
1577.83
|
1577.83
|
Shag’al
|
M3
|
498.03
|
1493.7
|
-
|
1532.4
|
1609.02
|
5133.33
|
256.3
|
242
|
1152.6
|
1214.2
|
756.17
|
756.17
|
756.17
|
But toshi
|
M3
|
38.31
|
-
|
-
|
-
|
574.65
|
612.96
|
18.8
|
19.51
|
114.93
|
114.93
|
114.93
|
114.93
|
114.93
|
Dumoloq yog’och
|
M3
|
38.31
|
-
|
153.24
|
22.9
|
42.14
|
256.59
|
20.6
|
17.71
|
43.65
|
43.65
|
43.65
|
43.65
|
43.65
|
Kesilgan taxta
|
M3
|
38.31
|
-
|
191.55
|
-
|
325.4
|
555.26
|
20.25
|
18.06
|
168.14
|
122.6
|
75.4
|
75.424
|
75.435
|
Metall
|
Tn
|
2.49
|
-
|
455.89
|
0.86
|
85.43
|
544.67
|
1.67
|
0.82
|
92.3
|
86.4
|
114.2
|
124.64
|
124.64
|
Rulonni materiallar
|
M2
|
114.9
|
-
|
3064.8
|
-
|
6895.8
|
10075.5
|
98.4
|
16.5
|
1289.7
|
2238.8
|
1790.8
|
2378.1
|
2378.1
|
Mix, boltlar
|
Kg
|
704.9
|
-
|
153.24
|
536.34
|
282.48
|
2099.9
|
389.6
|
315.3
|
231.3
|
156.2
|
258.7
|
374.4
|
374.4
|
|
| |